PJM proposes single one-year study for large load and generation requests in Nov. 16 FERC filing

PJM Interconnection filed a Fast Energization Process at FERC on Nov. 16, 2026, that would study large load and generation interconnection requests together in one one-year review, about twice as fast as the current process, according to PJM. Most major U.S. grid operators have now filed responses to FERC's June show cause orders, including CAISO, MISO and NYISO. ISO New England filed on Friday and says it will file details later this year, and the Southwest Power Pool is slated to file by Friday.

Why it matters

Interconnection timelines, cost allocation, flexible service options and bring-your-own-capacity requirements are being rewritten across several regions, so builders and AI strategy leads should track each filing as these rules would shape site selection and speed to power.

Original reporting: Utility Dive