NRG agrees to sell about 4.9 GW of gas plants to LS Power for $4B

NRG Energy agreed to sell around 4.9 GW of gas capacity in ISO-New England, ERCOT and NYISO to LS Power for $4 billion, about eight times the plants' $500 million annual adjusted EBITDA, CEO Robert Gaudette said on Nov. 9. NRG plans to use $1 billion for a stock buyback and $2 billion for debt reduction, and the sale is expected to close in the second quarter of 2027, subject to regulatory approvals. Gaudette said the 1.2-GW Jack County plant implies about $1,400/kW, versus just above $1,000/kW for 1.5 GW of new gas generation NRG is developing in Texas.

Why it matters

The roughly $1,400/kW implied price for an existing Texas plant, against just above $1,000/kW cited by NRG for new Texas builds, offers a reference point for teams weighing gas capex for data center supply.