Appalachian Power to invest $17B in about 3 GW of new West Virginia gas plants by 2031

West Virginia Gov. Patrick Morrisey said on November 12 that Appalachian Power will invest $17 billion in new gas-fired plants expected to add about 3 GW by 2031, plus a separate $7.5 billion for upgrades to existing coal plants through 2050. Three gas projects are planned across the state, with locations and other details to be announced later. The governor's office says the work falls under a ratepayer protection pledge meant to keep new generation costs off customer bills.

Why it matters

Builders and AI strategy leads sizing up West Virginia should note that about 3 GW of new gas capacity is announced for 2031 but sites are not yet named, and the buildout leans on gas and coal rather than low-carbon supply.

Original reporting: POWER Magazine