Indiana regulators approve $737M AES plan to serve 390-MW Google data center in Monrovia
The Indiana Utility Regulatory Commission approved, 5-0, AES Indiana's plan to build or acquire generation, storage and grid assets for a 390-MW Google data center in Monrovia, at an estimated project cost of about $737 million (Oct. 7 order). Google will pay about $32 million upfront for the direct connection, while $73.8 million in network upgrades goes into the transmission rate base and is recovered from all customers. Consumer advocates say this shifts costs to other ratepayers, while AES says Google's contract revenue will more than offset residential customers' share.
The order shows how regulators may treat regional network upgrades as system-wide benefits rather than direct costs of a large load, a cost allocation question developers and AI strategy leads should plan for in utility negotiations.
Related headlines
- AMPERA to go public via Berto SPAC merger at about $900M pre-money equity value
- CyrusOne and KEPCO top out 48MW OSK1 data center in Osaka, first phase due Q1 2028
- Microsoft files for 316.7-acre, five-building data center campus in Mecklenburg County, Virginia
- 16 U.S. data center projects stopped in Q3 2026, up from 7 a year earlier, Relae says
- Anthropic to begin Nasdaq trading as ANT on Nov. 19, with shares expected near $83 to $85