Riot Platforms signs 910MW, 15-year lease worth $28bn with unnamed AI lab at Corsicana, Texas

Riot Platforms signed a 910MW IT capacity triple-net lease for its Corsicana campus in Navarro County, Texas, running 15 years with two five-year extensions. The contract is valued at $28 billion, rising to $54 billion if all extensions are exercised. Capacity is to be delivered in phases: 400MW in September 2027, 200MW in January 2028 and 310MW in July 2028.

Why it matters

Riot says total capital costs of about $6 million per IT megawatt are roughly half those of a Tier 3 build, a benchmark for builders and AI strategy leads weighing leased capacity against self-build costs and risk.