SpaceXAI seeks Arizona permit for data center campus of up to 6GW on 747 acres in Cochise County

SpaceXAI, through affiliate Tombstone Resources LLC, has applied to Cochise County for a special development permit for up to nine data center buildings on two plots totaling 747 acres near Willcox Playa, with the company claiming 6GW at full build-out in four 1.5GW stages. The company says it will spend about $3.6 billion on power infrastructure, including $500 million for phase one, and plans a 24GWh battery energy storage system. A zoning decision is scheduled for December 9, and construction could start in March 2027 if approved.

Why it matters

The proposal ties compute timing to grid upgrades the developer says it will fund and to on-site storage meant to limit grid impact, a model that builders and AI strategy leads may see more often as interconnection becomes the main constraint.

Original reporting: Data Center Dynamics