PJM backstop procurement for data centers could shrink to 630 MW from 6.8 GW, Jefferies says
PJM filed a revised reliability backstop procurement (RBP) proposal with FERC on Oct. 29, 2026, targeting a March 1 start, about seven months later than planned. The original target was a 6.8-GW shortfall from the 2028/29 base residual auction, but Jefferies analysts said the procurement could fall to roughly 630 MW after PPL Electric, FirstEnergy and AES Ohio cut near-term large-load forecasts by 6.5 GW. Separately, a Charles River Associates analysis found PJM could face a roughly 11.5-GW shortfall by 2030. PJM would close the bid window March 28, set the final target April 28 and post results May 10.
Builders and AI strategy leads in PJM should expect the backstop procurement size, collateral rules and state cost-recovery mechanisms to keep shifting, which affects interconnection timing and who carries the cost of capacity for new large loads.
Related headlines
- AMPERA to go public via Berto SPAC merger at about $900M pre-money equity value
- CyrusOne and KEPCO top out 48MW OSK1 data center in Osaka, first phase due Q1 2028
- Microsoft files for 316.7-acre, five-building data center campus in Mecklenburg County, Virginia
- 16 U.S. data center projects stopped in Q3 2026, up from 7 a year earlier, Relae says
- Anthropic to begin Nasdaq trading as ANT on Nov. 19, with shares expected near $83 to $85