Prometheus Hyperscale exits 1.2 GW Casper, Wyoming data center project announced in October 2025
Prometheus Hyperscale has withdrawn from a planned 1.2 GW, 940-acre campus near Casper in Natrona County, Wyoming, which was announced in October 2025 with Spiritus and Casper Carbon Capture. The plans included natural gas power from Spiritus affiliate Orchard Power and carbon capture, and no building permits had been filed. Landowner Falls Ranch says work will continue through a new development company, but this has not been independently confirmed.
Why it matters
The exit before any building permits were filed shows that developer commitments to gigawatt-scale, gas-powered campuses can change during pre-permitting, even when local officials are supportive.
Related headlines
- AMPERA to go public via Berto SPAC merger at about $900M pre-money equity value
- CyrusOne and KEPCO top out 48MW OSK1 data center in Osaka, first phase due Q1 2028
- Microsoft files for 316.7-acre, five-building data center campus in Mecklenburg County, Virginia
- Anthropic to begin Nasdaq trading as ANT on Nov. 19, with shares expected near $83 to $85
- Google cut Scope 2 market-based emissions 3% in 2025 despite 37% load growth, citing granular certificates