Xcel Energy lifts five-year capital plan 17% to $70B, with $7B for contracted data centers

Xcel Energy unveiled a $70 billion five-year capital plan on its Oct. 29, 2026 earnings call, up from $60 billion. It includes 9.2 GW of renewables (about $21.7 billion), 2.3 GW of storage and 3.3 GW of natural gas, plus about $7 billion for data center projects already under contract. The company expects to sign 4 GW of new data center agreements by year end 2027, and says up to $10 billion more could be spent beyond the plan. It will fund the plan with $26 billion in debt and $8 billion in equity.

Why it matters

Data center developers in Xcel territory can see a utility tying about $7 billion of contracted-load spending to a stated principle that existing customers should not subsidize new large loads.

Original reporting: Utility Dive