Proposed PCE metric shows share of provisioned power available for compute: 0.705 at 20 MW site, 0.79 at 100 MW campus
Airsys Cooling Technologies defined power compute effectiveness (PCE) in a paper published by the Open Compute Project. PCE is the share of a data center's provisioned power allocated to compute rather than cooling, electrical losses and auxiliary systems. In the paper's two real-world examples, a 20 MW colocation site scored 0.705 and a 100 MW hyperscale campus scored 0.79. There is no validated industry average yet, and Airsys says its ranges (0.50 to 0.65 for older air-cooled sites, high 0.80s for well-designed liquid-cooled sites) are directional.
Why it matters
PCE offers builders and AI strategy leads a way to test whether cooling or electrical retrofits can free capacity inside a fixed power envelope before they pursue a new utility connection.
Related headlines
- AMPERA to go public via Berto SPAC merger at about $900M pre-money equity value
- CyrusOne and KEPCO top out 48MW OSK1 data center in Osaka, first phase due Q1 2028
- Microsoft files for 316.7-acre, five-building data center campus in Mecklenburg County, Virginia
- Anthropic to begin Nasdaq trading as ANT on Nov. 19, with shares expected near $83 to $85
- Google commits to replenish more water than it consumes at its sites by 2030, with $100M+ in 2026 funding