Microsoft ends contract for Nscale's 50 MW Loughton, UK AI campus after power connection delays
Microsoft terminated its contract for Nscale's planned AI data center in Loughton, England, a project announced in 2025 as 50 MW, scalable to 90 MW, with 23,040 Nvidia GB300 GPUs for Azure. Nscale confirmed the termination. The Guardian reported that UK Power Networks told the company it could not supply enough electricity until the early to mid-2030s. Nscale says it remains committed to the site and is exploring alternative power, and no financial consequences have been disclosed.
Why it matters
A signed customer contract and financing do not guarantee an energized site, so grid connection dates need to be treated as a core schedule and revenue risk, especially for developers that depend on a few anchor customers.
Related headlines
- AMPERA to go public via Berto SPAC merger at about $900M pre-money equity value
- CyrusOne and KEPCO top out 48MW OSK1 data center in Osaka, first phase due Q1 2028
- Microsoft files for 316.7-acre, five-building data center campus in Mecklenburg County, Virginia
- 16 U.S. data center projects stopped in Q3 2026, up from 7 a year earlier, Relae says
- Anthropic to begin Nasdaq trading as ANT on Nov. 19, with shares expected near $83 to $85